Fees and charges

Fees and charges

There are costs associated with connecting to our network. The fee for a standard connection is determined by the type and size of the water, sewerage or fire service you request. You can nominate the size of service you require during the application process, or we can advise you of the most suitable size.

Fees and charges schedule

This page is a tool to provide you with an estimated cost to help you decide if you want to apply. It is based on your own understanding of your property and the work you would like to complete. We recommend visiting our Connections Estimator Map first to understand if the connection services you are considering are available, and estimate the distance required to complete the connection. If an extension or upgrade is required to service your property, you will be responsible for these costs.

Additional connections costs may occur if:

  • the connection from the main to your property is greater than 12 metres
  • the depth of the connection is 3.0m or deeper
  • if difficult construction conditions exist (for example: existing services and infrastructure in the construction path, underground water, trees, rocks or requirements for traffic management)

Find out more about standard and non standard connections here.

We will estimate the cost of this work and provide you with a fixed price invoice once we have assessed your submitted application and a site visit is completed. Your application’s lodgement fee will be deducted from the final construction cost if your project goes ahead. Any financial quote provided will be valid for 60 calendar days from the date of issue.

Augmentation charges also apply in designated areas throughout the state.

Smart meter pricing

We offer a range of smart meters with different technology features.

To access the benefits of a smart meter, you will need to pay an installation fee and then an annual fee each year (you can opt out at any time). We offer a range of different smart meters and provide a personalised quote based on your needs, property and location. Smart meter installations typically range from $1,250 to $6,750*.

All smart meters have an annual fee of $128.65 (for standard smart meters).

Learn more about smart meters

Timeframes

Your online application will take 10-15 minutes to complete.

After receiving a completed application we will endeavour to assess and invoice you within 20 business days.

Every connection project and site is different and there are various factors outside of our control that can impact cost and delivery timeframes.

We are committed to delivering connection services in accordance with our regulatory service standards. After you have paid your invoice we will use our best endeavours to construct/activate your service within the following timeframes to meet regulatory service standards:
  • a standard water connection within 25 business days
  • a non-standard water connection within 35 business days
  • a standard sewerage connection within 30 business days
  • a non-standard sewerage connection within 50 business days
  • Connections that require extension or upgrade of the supply network may take longer in the construction phase because they are dependent on extension or upgrade works separate to the connection works. We will detail the expected construction timeframe in your approval letter.

    Our live tracker is available 24/7 and will let you know where your connection project is up to in the application process.

    How to prepare your application

    Whether you are applying for a new connection, making alterations to an existing service or want to disconnect, we can help you make sure you have all the information and supporting documents you need to submit an accurate connections application. Follow the steps on our Application checklist page here.

    • Major faults

    • Underway

    • Polkinghorns Rd
    • Arthurton
    • 18/06/2020
    • Water Supply On
    • 18/06/2020 03:05 PM - We are attending to an incident in Arthurton with no interruption to the water supply. The safety of our crews and customers comes first, and we always aim to minimise inconvenience by restoring services as quickly as we can. Reference Number WO: 07505663.
    • See all major faults

    • Scheduled works

    • Underway
    • Spruance Rd
    • Elizabeth East
    • 11/06/2021
    • Temporary Supply Interruption
    • Estimated start time and water supply off: 15/06/2021 09:00 AM
      Estimated restore time and water supply back on: 15/06/2021 04:00 PM

      We’re improving your services and undertaking maintenance work in Elizabeth East. Sometimes our crews need to temporarily interrupt the water supply to our customers and/or manage traffic while they are working. Temporary traffic management may remain in place until reinstatement of the impacted road is complete. We always aim to minimise inconvenience by restoring services as safely and quickly as we can.